Chapel Rock-to-Pincher Creek Transmission Development (7064)
With the evolving electricity landscape, the AESO has worked diligently to ensure the previously approved transmission development in southwest Alberta continues to be the right plan for the transmission system for all Albertans. Specifically, the need for this transmission development reinforcement was approved by the Alberta Utilities Commission (AUC) as part of the Southern Alberta Transmission Reinforcement Needs Identification Document (NID) on September 8, 2009. The NID, including all appendices, engagement material and amendments approved by the AUC are located in “Archived Materials” below.
The Chapel Rock–to–Pincher Creek Transmission Development project includes:
- Construction of the previously approved Chapel Rock substation will proceed.
- One new 240 kV transmission circuit will connect the new Chapel Rock substation to one of two existing substations – either Castle Rock Ridge or Goose Lake. Both substations present technically viable solutions. Based on additional work as part of the planning process, and taking stakeholder feedback into consideration, it was determined that a second 240 kV transmission line is not required within the next five-10 years and will remain as part of our long-term plans for the area.
Key materials
- Update Letter [Posted: Feb. 1, 2022]
- 2020 Update Letter [Posted: July 30, 2020]
- 2019 Transmission Projects information session [Posted: Oct. 4, 2019]
- 2019 Transmission Projects webinar recording [Posted: Oct. 4, 2019]
- Update Letter [Posted: Feb. 28, 2019]
- Chapel Rock–to–Pincher Creek Transmission Development Update (Newsletter) [Posted: Sept. 2018]
- Moving forward with transmission development in your area (Newsletter) [Posted: Jan. 2018]
- AESO Presentation – AltaLink Community Workshops [Posted: April 2018]
<iframe width="560" height="315" src="https://www.youtube.com/embed/8n6Ug9IXrp8" frameborder="0" allow="autoplay; encrypted-media" allowfullscreen></iframe>
This video has been updated to reflect the current transmission solution proposed by the AESO. To view our newsletter please click here. To view the original video please click here.
The Chapel Rock-to-Pincher Creek transmission development will also contribute to the restoration of the Alberta-British Columbia intertie to, or near to, its path rating. Please visit www.aeso.ca/grid/projects/Intertie-Restoration for more information on the Alberta-British Columbia Intertie Restoration project.
Archived material
Contact us
If you have any suggestions, questions or concerns please contact Stakeholder Relations at stakeholder.relations@aeso.ca or 1-888-866-2959.