    Laramide Battery Storage Facility Connection (2520)

    2569059 Alberta Inc. (Enfinite) has applied to the AESO for transmission system access to connect its proposed Laramide Battery Storage Facility (Facility) in the Blackie area. Enfinite’s request can be met by the following solution:

    • Add one 240 kV transmission line to connect the Facility to the existing Foothills 237S substation in a radial configuration.
    • Modify the existing Foothills 237S substation, including adding two 240 kV circuit breakers.
    • Add or modify associated equipment as required for the above transmission developments.

    Market Participant Notification

    Need Overview

    Latest updates

    • Dec. 11, 2024 Market Participant Notification for the Laramide Battery Storage Facility Connection
    • Oct. 23, 2024 Need Overview: Laramide Battery Storage Facility Connection