    Oyen Wind Power Project Connection (2356)

    Renewable Energy Systems Canada Inc. (RESC) has applied to the AESO for transmission system access to connect its proposed Oyen Wind Power Project (Facility) in the Oyen area. RESC’s request can be met by the following solution:

    • Add one 240 kV transmission line to connect the Facility to the existing Lanfine 959S substation in a radial configuration.
    • Modify the Lanfine 959S substation, including adding one 240 kV circuit breaker.
    • Add or modify associated equipment as required for the above transmission developments.

    Abbreviated Needs Approval Process: Approval

    The AESO approved the Oyen Wind Power Project Connection under Section 501.3 of the ISO rules, Abbreviated Needs Approval Process.

    Abbreviated Needs Approval Process: Notice of Consideration

    The AESO intends to consider the need for the Oyen Wind Power Project Connection for approval under Section 501.3 of the ISO rules, Abbreviated Needs Approval Process, (ANAP Rule) on or after November 28, 2024. If stakeholders have any questions or concerns, please contact the AESO before this date.

    The AESO has determined that the Project is eligible for consideration under the ANAP Rule because the following eligibility criteria have been met:

    • Project costs are estimated to be $13M and were classified as participant-related in accordance with the ISO tariff 
    • the AESO has completed a participant involvement program (PIP) in accordance with the guidelines in Alberta Utilities Commission Rule 007; 
    •  the Project is not anticipated to result in significant environmental effects; and
    • No concerns or objections with the need for the Project have been raised. Prior to making its approval decision, the AESO will address additional stakeholder concerns that arise, if any.

    Supporting information about this Project is available in the following documents:

    Market Participant Notification

    Need Overview

    Latest updates

    • Nov. 28, 2024 Abbreviated Needs Approval Process: Notice of Approval for the Oyen Wind Power Project Connection
    • Nov. 13, 2024 Abbreviated Needs Approval Process: Notice of Consideration for the Oyen Wind Power Project Connection
    • Aug. 26, 2024 Market Participant Notification for the Oyen Wind Power Project Connection in the Oyen Area
    • Feb. 7, 2024 Need Overview: Oyen Wind Power Project Connection