Scotford 409S Substation Upgrade (2513)
Shell Canada Limited (Shell) has applied to the AESO for transmission system access to improve the reliability of electricity service to the Shell industrial facility in the Fort Saskatchewan Area. Shell’s request can be met by the following solution:
- Upgrade the existing Scotford 409S substation, including adding one 138/25 kV transformer and two 138 kV circuit breakers.
- Add or modify associated equipment as required for the above transmission developments.
Need Overview
- Update - Need for the Scotford 409S Substation Upgrade [Posted: Nov. 26, 2024]
- Need for the Scotford 409S Substation Upgrade in the Fort Saskatchewan area [Posted: April 21, 2023]
Latest updates
- Updated Need Overview: Scotford 409S Substation Upgrade
- Need Overview: Scotford 409S Substation Upgrade