Addition of Voltage Support at Rycroft 730S Substation (1784)
Transmission reinforcement is required in the Rycroft area to accommodate future growth in electricity demand and ensure reliability. The AESO is expecting voltage below acceptable limits in this area under certain operating conditions. To maintain reliability, the AESO is proposing to add new voltage support equipment inside the existing Rycroft 730S substation. On May 3, 2019, the AUC approved the AESO’s NID.
Key Documents
- Addition of Voltage Support at Rycroft 730S Substation Project Newsletter [Posted: October 31, 2017]
Notification of regulatory filing advertisement
- Notice of Filing for the Addition of Voltage Support at Rycroft 730S Substation [Posted: November 30, 2017]
Needs Identification Document
Addition of Voltage Support at Rycroft 730S Substation Needs Identification Document [Posted: December 15, 2017]
Appendix A - AESO Planning Studies
Appendix B - AESO Load and Generation Forecast
Appendix C - Capital Cost Estimates from TFO
Appendix D - AESO Participation Involvement Program Summary
Appendix E - TFO's Land Impact Assessment under AUC Rule 007, s.6.1. NID 7(9)
Appendix F - Single Line Diagram
Appendix G - Transmission Planning Criteria - Basis and Assumptions